Grotonwood Projects and Estimated Costs
Pine Lodge – Repair and Paint the Front Exterior Entrance – Materials $50.00
Pine Lodge – Repair Back Left Porch and Replace Wheelchair Ramp and Paint Materials $1500.00
Memorial Lodge – Front Door Area – Pour new Cement Ramp to Door – Materials $100.00.
Memorial Lodge – Make repairs and paint fire escape – Materials $75.00. Memorial Lodge – Paint or cover exterior trim and paint exterior doors Materials – Paint Trim $100.00 Cover trim w/aluminum - $600.00 Paint Exterior Doors - $50.00
Gym – Garden Areas Front and Side – New Landscape Ties and Block Wall Landscape where needed outside Gym Materials – Landscape Ties - $1500.00 Blockwall - $2500.00 Landscaping - $250.00
Adult Center – Clean, repair, and wood preserve walkway ramp. Materials -$100.00
Adult Center – Clean landscaping and replace overgrown plants Materials – Clean up $100.00 Replace Plants - $250.00
Adult Center – Paint fire escape trim on both sides of building. Materials - $60.00
Family Center Dining Hall – Re-shingle Roof. Materials - $3500.00
Family Center Red Cabin – Repair porches, water seal and paint trim. Materials - $75.00.
Family Center Green Cabin – Repair porches and wheelchair ramp, water seal and paint trim. Materials - $100.00. Family Center Green Cabin – Pour cement ramp at end of Wheelchair Ramp – Materials - $100.00
Family Center Gold Cabin – Repair Porches and water seal and paint trim. Materials - $75.00
Family Center Red Cabin – Landscape garden in front of building (edge out, mulch, and add landscape or flowers) Materials - $100.00.
Family Center Green Cabin - Landscape garden in front of building (edge out, mulch, and add landscape or flowers) Materials - $100.00.
Family Center Gold Cabin - Landscape garden in front of building (edge out, mulch, and add landscape or flowers) Materials - $100.00
Pioneer Valley Shelter 1 – Flooring and Curtains, Clean Up for Summer, Repair Doors, Screens, and Steps. Materials - $200.00
Pioneer Valley Shelter 2 – Flooring and Curtains, Clean Up for Summer, Repair Doors, Screens, and Steps. Materials - $200.00
Pioneer Valley #1 Service Building – Clean Up, make repairs to shower area for summer. Repair Door Screen – Materials $300.00.
Pioneer Valley #2 Service Building – Re-shingle for Summer. Materials - $800.00.
Wood Cutting all over camp, pick up brush in program areas all over camp. Bring your own saws and brush trimmers.
Oceanwood Projects and Estimated Costs Ataloa Cabin #9 - New Screen/Storm Doors & Carpet - $600.00 Ataloa Cabin #8 - Framing, sheetrock, doors, trim, and carpet - $3000.00 Ataloa Cabin #7 - Framing, sheetrock, doors, trim, carpet and electric - $3500.00 Lawton Lodge - Roof stripped and shingled - $4000.00 |